Back to projects

Rural Municipality of Porcupine No. 395, Copeau Bridge Replacement

Porcupine No. 395, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$150,030
Federal share17%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 11, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 15, 2022(actual)
Construction end
Nov 9, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2022
  • Construction end7 months lateforecast Mar 31, 2023

Also in Porcupine No. 395