Rural Municipality of Porcupine No. 395, Copeau Bridge Replacement
Porcupine No. 395, Saskatchewan
Federal contribution
$150,030
Federal share17%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2021
20222023
Built
Approved 8 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Porcupine No. 395
- Construction start
- Sep 15, 2022(actual)
- Construction end
- Nov 9, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2022
- Construction end7 months lateforecast Mar 31, 2023
Also in Porcupine No. 395
- RM of Porcupine No. 395, Wolstenholme Bridge$166.7K
- Rural Municipality of Porcupine No. 395, Farley Bridge Replacement$166.7K
- Hintz Bridge over the Prairie River in the Rural Municipality of Porcupine No. 395$116.7K
- North South Peggs Bridge over McKillop Creek in the Rural Municipality of Porcupine$115.2K
- Belchamber Bridge over Shand Creek in the Regional Municipality of Porcupine No. 395$114.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59427 in the federal list. How to read these figures.