RM of Porcupine No. 395, Wolstenholme Bridge
Porcupine No. 395, Saskatchewan
Federal contribution
$166,700
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2022
202320242025
Built
Approved 8 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Porcupine No. 395
- Construction start
- Jan 2, 2025(actual)
- Construction end
- May 26, 2025(actual)
Against the original forecast
- Construction end8 weeks lateforecast Mar 31, 2025
Also in Porcupine No. 395
- Rural Municipality of Porcupine No. 395, Farley Bridge Replacement$166.7K
- Rural Municipality of Porcupine No. 395, Copeau Bridge Replacement$150.0K
- Hintz Bridge over the Prairie River in the Rural Municipality of Porcupine No. 395$116.7K
- North South Peggs Bridge over McKillop Creek in the Rural Municipality of Porcupine$115.2K
- Belchamber Bridge over Shand Creek in the Regional Municipality of Porcupine No. 395$114.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61383 in the federal list. How to read these figures.