Schedule
Announced and approvedMar 9, 2021
202120222023
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Big River First Nation
- Construction start
- May 1, 2021(actual)
- Construction end
- Sep 30, 2023(actual)
Against the original forecast
- Construction start10 months lateforecast Jul 1, 2020
- Construction end13 months lateforecast Aug 31, 2022