Big River First Nation Arena Build

Debden, Saskatchewan

completeRecreationCCRIS
Federal contribution
$7.1M
$7,101,750
Federal share75%

of $9.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 9, 2021
202120222023
Built

Approved 5 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Big River First Nation
Construction start
May 1, 2021(actual)
Construction end
Sep 30, 2023(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 1, 2020
  • Construction end13 months lateforecast Aug 31, 2022