Debden Community Centre Green is Clear Upgrades
Federal contribution
$118,320
Federal share79%
of $149.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 7, 2022
20222023
Built
Approved 9 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Corporation du centre communautaire de Debden Community Centre
- Construction start
- Dec 12, 2022(actual)
- Construction end
- Mar 31, 2023(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 1, 2022
- Construction end8 months lateforecast Jul 31, 2022
Also in Debden
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62320 in the federal list. How to read these figures.