Debden Community Centre Green is Clear Upgrades

Debden, Saskatchewan

completeRecreationGICB
Federal contribution
$118,320
Federal share79%

of $149.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 7, 2022
20222023
Built

Approved 9 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Dec 12, 2022(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2022
  • Construction end8 months lateforecast Jul 31, 2022

Also in Debden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62320 in the federal list. How to read these figures.