Village of Debden Water Treatment Upgrade
Federal contribution
$466,202
Federal share40%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 29, 2024
today
2024202520262027
BuiltForecast
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Debden
- Construction start
- Jul 1, 2025(actual)
- Construction end
- Mar 31, 2027(forecast)