Town of Fort Qu'Appelle Rexentre HVAC & Mechanical Upgrades

Fort Qu'Appelle, Saskatchewan

completeRecreationCCRIS
Federal contribution
$90,240
Federal share40%

of $225.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
2022
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Fort Qu'Appelle
Construction start
Apr 1, 2022(actual)
Construction end
Oct 26, 2022(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Aug 31, 2022