New Water and Wastewater Mains and Pump Station Upgrade

Fort Qu'Appelle, Saskatchewan

completeWastewaterCWWF
Federal contribution
$885,852
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Fort Qu'Appelle
Construction start
Sep 26, 2017(actual)
Construction end
Aug 31, 2019(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2017

Also in Fort Qu'Appelle

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50020 in the federal list. How to read these figures.