Town of Fort Qu'Appelle - Rexentre Infrastructure Improvements
Federal contribution
$282,064
Federal share40%
of $705.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
2022
Built
Approved 7 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Fort Qu'Appelle
- Construction start
- May 1, 2022(actual)
- Construction end
- Sep 15, 2022(actual)
Against the original forecast
- Construction end4 months earlyforecast Dec 31, 2022
Also in Fort Qu'Appelle
- Town of Fort Qu'Appelle Water Treatment Plant Improvements$958.0K
- New Water and Wastewater Mains and Pump Station Upgrade$885.9K
- Sioux Ave. Street Improvement$155.0K
- Town of Fort Qu'Appelle Rexentre HVAC & Mechanical Upgrades$90.2K
- North Valley Waste Management Authority Inc. - Decommissioning Project 2021$53.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59549 in the federal list. How to read these figures.