Rankin Inlet Wastewater Treatment Plant Upgrades Planning
Federal contribution
$159,108
Federal share100%
of $159.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 20, 2022
2022
Built
Approved 16 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Government of Nunavut
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Jun 29, 2022(actual)
Against the original forecast
- Construction end9 months earlyforecast Mar 31, 2023
Also in Rankin Inlet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57455 in the federal list. How to read these figures.