Kivalliq Seniors Long Term Care Facility
Federal contribution
$25.0M
$25,000,000
Federal share41%
of $61.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 4, 2024
2019202120232025
Built
Approved 7 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Government of Nunavut
- Construction start
- Apr 1, 2019(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction start2.2 years earlyforecast Jun 1, 2021
- Construction end2.2 years lateforecast Dec 31, 2023
Also in Rankin Inlet