Rankin Inlet Wastewater Treatment Facility Detailed Design/Construction

Rankin Inlet, Nunavut

approvedWastewaterGIS
Federal contribution
$18.0M
$18,043,000
Federal share75%

of $24.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 4, 2024
today
2024202620282030
BuiltForecast

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Government of Nunavut
Construction start
Apr 1, 2027(forecast)
Construction end
Dec 31, 2030(forecast)