Rankin Inlet Wastewater Treatment Facility Detailed Design/Construction
Federal contribution
$18.0M
$18,043,000
Federal share75%
of $24.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 4, 2024
today
2024202620282030
BuiltForecast
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Government of Nunavut
- Construction start
- Apr 1, 2027(forecast)
- Construction end
- Dec 31, 2030(forecast)
Also in Rankin Inlet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66968 in the federal list. How to read these figures.