Rehabilitation of 1875 Log School House and 1850 Log Home, Exterior Exhibits at Bruce County Museum and Cultural Centre
Federal contribution
$14,568
Federal share40%
of $36.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 8, 2021
2021
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Bruce County Museum and Cultural Centre
- Construction start
- Feb 26, 2021(actual)
- Construction end
- Apr 24, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Dec 7, 2020
- Construction end3 months lateforecast Jan 29, 2021
Also in Saugeen Shores
- McEwing Bridge Replacement$1.1M
- Bruce County Road 17$434.8K
- Port Elgin - Storm Sewer outlet installation$338.4K
- Storm Sewer installation to eliminate failing infiltration galleries and watermain upgrade to meet growth demand (Outlet ca. 40 blocks in Port Elgin.)$272.8K
- Installation of New Watermain on Concession 6 to Facilitate Expansion for growth demand$221.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57542 in the federal list. How to read these figures.