McIntyre Headframe Restoration
Federal contribution
$350,800
Federal share40%
of $877.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Timmins
- Construction start
- Aug 3, 2021(actual)
- Construction end
- Jan 31, 2022(actual)
Against the original forecast
- Construction end4 weeks lateforecast Dec 31, 2021
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57581 in the federal list. How to read these figures.