Cambridge Public Library (Idea Exchange Hespeler Library) - Elevator Accessibility and Mechanical Refurbishment
Federal contribution
$47,960
Federal share40%
of $119.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2021
today
2021202320252027
BuiltForecast
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Cambridge
- Construction start
- Jun 1, 2026(forecast)
- Construction end
- Dec 31, 2026(forecast)
Also in Cambridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57654 in the federal list. How to read these figures.