Paisley Town Hall Accessibility
Federal contribution
$77,595
Federal share40%
of $194.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 8, 2021
20212022
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Arran-Elderslie
- Construction start
- Feb 7, 2022(actual)
- Construction end
- Jun 28, 2022(actual)