Back to projects

Harbour Passage – Phase 1 – Loyalist Plaza

Saint John, New Brunswick

completeActive TransportationCVRIS
Federal contribution
$8.0M
$7,996,000
Federal share80%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 19, 2021
2021202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Saint John
Construction start
Feb 11, 2022(actual)
Construction end
Jul 31, 2024(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jan 3, 2022
  • Construction end3 months earlyforecast Oct 31, 2024

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57775 in the federal list. How to read these figures.