Harbour Passage Phase 1 Loyalist Plaza
Federal contribution
$8.0M
$7,996,000
Federal share80%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 19, 2021
2021202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Saint John
- Construction start
- Feb 11, 2022(actual)
- Construction end
- Jul 31, 2024(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jan 3, 2022
- Construction end3 months earlyforecast Oct 31, 2024
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57775 in the federal list. How to read these figures.