Back to projects

Old Government House - Windows

Fredericton, New Brunswick

completeCultureCVRIS
Federal contribution
$480,000
Federal share80%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20212022
Built

Approved 8 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Apr 15, 2021(actual)
Construction end
Jan 17, 2022(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 14, 2021
  • Construction end5 weeks lateforecast Dec 11, 2021

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58063 in the federal list. How to read these figures.