Fredericton District Garage - Building Envelope

Fredericton, New Brunswick

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$880,000
Federal share80%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20212022
Built

Approved 8 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Aug 31, 2021(actual)
Construction end
Mar 31, 2022(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 10, 2021