Saint John Provincial Building - Elevator Modernization
Federal contribution
$364,800
Federal share80%
of $456.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
202120222023
Built
Approved 8 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Apr 14, 2021(actual)
- Construction end
- May 10, 2023(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 5, 2021
- Construction end5 months lateforecast Dec 17, 2022
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58069 in the federal list. How to read these figures.