Construction of a new arena
Federal contribution
$6.4M
$6,358,218
Federal share33%
of $19.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2021
today
202220232024202520262027
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Sainte-Thérèse
- Construction start
- Jun 13, 2025(forecast)
- Construction end
- Aug 24, 2027(forecast)
Also in Sainte-Thérèse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58128 in the federal list. How to read these figures.