Replacement of heat / cold production units and roof repair
Federal contribution
$3.4M
$3,396,803
Federal share80%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Jul 29, 2022(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 1, 2021
- Construction end16 months earlyforecast Dec 1, 2023
Also in Sainte-Thérèse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59591 in the federal list. How to read these figures.