Roof Repair of the Léger Wing
Federal contribution
$491,353
Federal share70%
of $701.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Lionel-Groulx
- Construction start
- May 31, 2021(actual)
- Construction end
- Dec 23, 2022(actual)
Also in Sainte-Thérèse