Back to projects

665 George St - Storm Water Management Upgrade

Fredericton, New Brunswick

completeWastewaterCVRIS
Federal contribution
$416,967
Federal share80%

of $521.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2021
Built

Approved 7 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Jun 24, 2021(actual)
Construction end
Sep 9, 2021(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2021
  • Construction end4 months earlyforecast Dec 31, 2021

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58155 in the federal list. How to read these figures.