Back to projects

Outdoor Sport Court and Field Renewal - Fredericton

Fredericton, New Brunswick

completeRecreationCVRIS
Federal contribution
$340,000
Federal share80%

of $425.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 5, 2021
2021
Built

Approved 8 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Fredericton
Construction start
Apr 19, 2021(actual)
Construction end
Nov 30, 2021(actual)

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58160 in the federal list. How to read these figures.