Saint John Regional Correctional Centre Mid Life Upgrades - Admissions
Federal contribution
$1.6M
$1,600,000
Federal share80%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20212022
Built
Approved 8 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Apr 8, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Jan 22, 2022
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58164 in the federal list. How to read these figures.