Back to projects

Richelieu Vanier Park - New Outdoor Pool

Ottawa, Ontario

approvedRecreationCCRIS
Federal contribution
$2.0M
$2,000,000
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2021
today
2021202320252027
BuiltForecast

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Ottawa
Construction start
Mar 31, 2026(forecast)
Construction end
Mar 31, 2027(forecast)

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58191 in the federal list. How to read these figures.