Provincial Building Refits - Space Rationalization
Federal contribution
$2.4M
$2,400,000
Federal share80%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20212022
Built
Approved 8 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Feb 9, 2021(actual)
- Construction end
- Mar 18, 2022(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Apr 5, 2021
- Construction end11 months earlyforecast Feb 25, 2023
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58202 in the federal list. How to read these figures.