Play Space Resurfacing

Lincoln, Ontario

completeRecreationCCRIS
Federal contribution
$362,783
Federal share40%

of $907.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 4, 2021
202120222023
Built

Approved 6 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Lincoln
Construction start
May 4, 2022(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction end2 months lateforecast Jul 1, 2023