Mayfield Recreation Complex - Infrastructure Improvements
Federal contribution
$203,100
Federal share62%
of $328.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 8, 2021
20212022202320242025
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Caledon
- Construction start
- Jul 22, 2021(actual)
- Construction end
- Aug 14, 2025(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Oct 1, 2025
Also in Caledon
- Old Bolton Fire Hall revitalization into a low carbon, multi-purpose Community Hub as part of Caledon's downtown Bolton Revitalization Plan.$4.3M
- Belfountain Conservation Area: Dam & Channel$3.2M
- Interconnection of Caledon East and Palgrave Water System$1.4M
- Water servicing for the communities of Campbells Cross and Victoria in Town of Caledon$1.4M
- Resurfacing - on the Forks of the Credit Road from Hurontario Street to West$1.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58208 in the federal list. How to read these figures.