Youville Centre Roof and HVAC
Federal contribution
$714,286
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 1, 2021
2021202220232024
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Centre Youville Centre Ottawa-Carleton Inc.
- Construction start
- May 1, 2023(actual)
- Construction end
- Dec 22, 2023(actual)