Back to projects

Youville Centre Roof and HVAC

Ottawa, Ontario

completeRecreationCCRIS
Federal contribution
$714,286
Federal share40%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2021
2021202220232024
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
May 1, 2023(actual)
Construction end
Dec 22, 2023(actual)

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58210 in the federal list. How to read these figures.