Fort Garry District Energy Upgrades

Winnipeg, Manitoba

underwayGreen EnergyGIS
Federal contribution
$14.1M
$14,069,200
Federal share40%

of $35.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2021
today
202220232024202520262027
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
University of Manitoba
Construction start
Jun 6, 2022(actual)
Construction end
Dec 31, 2026(forecast)

Against the original forecast

  • Construction start3 weeks lateforecast May 15, 2022

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58272 in the federal list. How to read these figures.