Dood Cristall Family YMCA Expansion

Brandon, Manitoba

completeRecreationRNIS
Federal contribution
$2.3M
$2,280,600
Federal share40%

of $5.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Feb 18, 2022(actual)
Construction end
Feb 29, 2024(actual)

Against the original forecast

  • Construction end4 months lateforecast Nov 1, 2023