Construction of an Aquatic Complex
Federal contribution
$10.0M
$10,000,000
Federal share32%
of $31.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 18, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Laval
- Construction start
- Feb 21, 2022(actual)
- Construction end
- Aug 26, 2024(actual)
Against the original forecast
- Construction start4 months earlyforecast Jun 14, 2022
Also in Laval
- The Société de transport de Laval garage expansion (Phase IV)$85.1M
- Acquisition of 94 Electric Buses$59.5M
- Updating drinking water treatment plants in Laval$46.8M
- Stabilization and revitalization work on the shore and Boulevard des Mille-Îles between Highway 25 and the eastern tip of Laval Island$25.3M
- Backflow controls of Monty sector - Laval$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58414 in the federal list. How to read these figures.