Bottle filling station; windows and exterior finish; heating, ventilation, air conditioning, locking up premises; hand washing station
Federal contribution
$721,180
Federal share80%
of $901.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Conseil Scolaire Catholique de District des Grandes-Rivieres
- Construction start
- May 3, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Feb 18, 2021
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58525 in the federal list. How to read these figures.