Fixed water filling stations project group
Federal contribution
$3,199
Federal share80%
of $4.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Conseil des Ecoles Catholiques du Centre Est de l'Ontario
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Sep 1, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 18, 2021
- Construction end7 months earlyforecast Mar 31, 2022
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58550 in the federal list. How to read these figures.