Unit Ventilators; WiFi Access Points; Rooftop HVAC Unit; Operable Windows; Building Automation System; Energy Recovery Ventilator

Hamilton, Ontario

completeVentilationCVRIS
Federal contribution
$4.9M
$4,856,080
Federal share80%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 1, 2021(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2023