Back to projects

HVAC; Bottled Water Refilling Stations; Partition Classroom Space; Automatic Door Opener Installation; Playground; Entrance Partition

Hamilton, Ontario

completeVentilationCVRIS
Federal contribution
$3.6M
$3,611,519
Federal share80%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 1, 2021(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2023

Also in Hamilton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58637 in the federal list. How to read these figures.