Optimizing Air Quality; Promoting Occupant Health and Safety
Federal contribution
$1.6M
$1,632,000
Federal share80%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
20222023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Huron-Superior Catholic District School Board
- Construction start
- Jun 17, 2021(actual)
- Construction end
- Aug 31, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 18, 2021
- Construction end4 months earlyforecast Dec 31, 2023
Also in Sault Ste. Marie