Ventilation Upgrade & Childcare space retrofits, Windows
Federal contribution
$2.1M
$2,140,000
Federal share80%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Algoma District School Board
- Construction start
- Mar 1, 2021(actual)
- Construction end
- Nov 30, 2021(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2022