Boiler system
Federal contribution
$591,230
Federal share80%
of $739.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
20222023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Conseil Scolaire Catholique de District des Grandes-Rivieres
- Construction start
- May 4, 2021(actual)
- Construction end
- Jan 31, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Feb 18, 2021
- Construction end11 months earlyforecast Dec 31, 2023
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58714 in the federal list. How to read these figures.