Harbour Passage - Phase 2

Saint John, New Brunswick

completeRecreationCCRIS
Federal contribution
$1.1M
$1,070,000
Federal share40%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 19, 2021
2021202220232024
Built
Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Saint John
Construction start
Jun 1, 2023(actual)
Construction end
Oct 24, 2024(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 15, 2023
  • Construction end3 months lateforecast Jul 30, 2024

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58773 in the federal list. How to read these figures.