Repair of the south side exits of the Centre de soins prolongés Grace Dart

Montréal-Ouest, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$520,000
Federal share80%

of $650.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 16, 2022(actual)
Construction end
Nov 2, 2022(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Dec 22, 2022