Back to projects

Front Bloc B roof straightening

Laval, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$2.0M
$2,035,774
Federal share29%

of $7.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep Montmorency
Construction start
May 25, 2022(actual)
Construction end
Aug 28, 2023(actual)

Against the original forecast

  • Construction end3 months lateforecast May 21, 2023