Upgrades to the oncology department

Sept-Îles, Quebec

completeVentilationCVRIS
Federal contribution
$526,257
Federal share80%

of $657.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 30, 2021(actual)
Construction end
Apr 19, 2022(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2021
  • Construction end4 months lateforecast Dec 31, 2021

Also in Sept-Îles