Upgrades to the oncology department
Federal contribution
$526,257
Federal share80%
of $657.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Côte-Nord
- Construction start
- Aug 30, 2021(actual)
- Construction end
- Apr 19, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2021
- Construction end4 months lateforecast Dec 31, 2021
Also in Sept-Îles
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58906 in the federal list. How to read these figures.