Generator for Alternate Emergency Operations Centre
Federal contribution
$177,568
Federal share80%
of $222.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Bruce
- Construction start
- Jul 1, 2021(actual)
- Construction end
- Jan 9, 2023(actual)
Also in Saugeen Shores
- McEwing Bridge Replacement$1.1M
- Bruce County Road 17$434.8K
- Port Elgin - Storm Sewer outlet installation$338.4K
- Storm Sewer installation to eliminate failing infiltration galleries and watermain upgrade to meet growth demand (Outlet ca. 40 blocks in Port Elgin.)$272.8K
- Installation of New Watermain on Concession 6 to Facilitate Expansion for growth demand$221.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58933 in the federal list. How to read these figures.