Municipal Office Rehabilitation

West Elgin, Ontario

completeVentilationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Municipality of West Elgin
Construction start
Sep 30, 2021(actual)
Construction end
Mar 4, 2022(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Mar 31, 2022