Upgrades to Municipal Buildings
Federal contribution
$79,880
Federal share80%
of $99.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Hilton Beach
- Construction start
- Oct 3, 2022(actual)
- Construction end
- Dec 19, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 15, 2022
Also in Hilton Beach
- Hilton Beach Community Centre Rehabilitation$51.1K
- Blower, rotating biological contactor Pump and Lift Station Pump installation$22.5K
- Upgrade Wastewater Plant$12.5K
- Upgrades to components of the Supervisory Control and Data Acquisition (SCADA) at the Wastewater Plant$9.6K
- Equipment Upgrades at the Water Treatment Plant for Chlorine analyzer, Turbidity meter and singer valve.$7.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58949 in the federal list. How to read these figures.