Upgrade Wastewater Plant
Federal contribution
$12,500
Federal share50%
of $25.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
2018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Hilton Beach
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2017
Also in Hilton Beach
- Upgrades to Municipal Buildings$79.9K
- Hilton Beach Community Centre Rehabilitation$51.1K
- Blower, rotating biological contactor Pump and Lift Station Pump installation$22.5K
- Upgrades to components of the Supervisory Control and Data Acquisition (SCADA) at the Wastewater Plant$9.6K
- Equipment Upgrades at the Water Treatment Plant for Chlorine analyzer, Turbidity meter and singer valve.$7.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49600 in the federal list. How to read these figures.