Equipment Upgrades at the Water Treatment Plant for Chlorine analyzer, Turbidity meter and singer valve.

Hilton Beach, Ontario

completeDrinking WaterCWWF
Federal contribution
$7,500
Federal share50%

of $15.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Hilton Beach
Construction start
Nov 5, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2017
  • Construction end3 months lateforecast Jun 1, 2018

Also in Hilton Beach