Modification of the J-Wing ventilation system
Federal contribution
$520,000
Federal share80%
of $650.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Mauricie-et-du-Centre-du-Québec.
- Construction start
- Jul 5, 2021(actual)
- Construction end
- Jun 2, 2023(actual)
Against the original forecast
- Construction end6 months lateforecast Dec 6, 2022
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58968 in the federal list. How to read these figures.